Designed for spares from day one
Spare-parts problems are usually designed in, not caused by the service team. A machine built with an unbranded controller board or a custom-wound motor can stop for weeks waiting for one part. We avoid that at design stage by building on a small set of standard, widely distributed components:
| Function | Standard make on MEF machines | Why it matters for spares |
|---|---|---|
| PLC and HMI | Siemens S7-1200 / S7-1500 (Allen-Bradley on request) | Authorised distributors across India and most export markets |
| Servo drives and motors | Siemens V90 or Inovance | Catalogue parts with published successors when models change |
| Pneumatics | SMC | Valves, cylinders and vacuum parts available off the shelf in most industrial cities |
| Switchgear | Schneider | MCBs, contactors and relays stocked by electrical dealers everywhere |
| Vision | Basler cameras | Standard industrial cameras and lenses, not a sealed proprietary box |
| Robots | ABB, Yamaha or KUKA | Manufacturer service networks alongside ours |
Every machine ships with a bill of materials carrying the manufacturer's own part number for each bought-out item - the SMC or Siemens order code, not an internal code that only we can decode. If your plant is far from Pune, or a part is needed tonight, your maintenance team can buy it from a local distributor using the BOM alone.
"Will the BOM show manufacturer part numbers for every bought-out component?" If the answer is no, you are committing to buy every sensor and valve from that supplier for the life of the machine.
The recommended spares list: Critical, Wear and Consumable
With every machine we supply a recommended spares list that sorts parts by how they fail and what happens when they do. Quantities depend on the machine and your shift pattern; the classes and examples below are typical for cartoners, fillers, vial loaders and end-of-line machines.
| Class | What it means | Typical examples | Suggested holding |
|---|---|---|---|
| Critical | Failure stops the machine; the part is not normally worn but can fail suddenly | Servo drive of the most common rating, safety relay, 24 V DC power supply, key proximity and photo sensors (product present, registration mark), solenoid valve of each type, encoder, vacuum generator | One of each type per plant; share across identical machines |
| Wear | Wears at a predictable rate with running hours | Vacuum cups and suction pads, seal jaws, heater cartridges and thermocouples, timing and conveyor belts, gripper fingers and pads, cutting knives, cam followers and bearings, filler piston seals, capping chuck inserts | Enough for one to two replacement cycles |
| Consumable | Used up in normal operation or maintenance | PTFE tape and cloth for sealing jaws, fuses, FRL filter elements, O-rings, lubricants, printer ribbons for coders | Min-stock rule below |
| Format / change parts | Product-specific, made to drawing, damaged rather than worn | Star wheels, guide rails, bucket inserts, carton magazine guides, forming tubes, capping heads | Spare set for the highest-volume format if damage risk is high |
The list is a starting point. After six months of running, your own consumption data is a better guide than any supplier's estimate, so review it at the first preventive maintenance visit. Wear-part life also depends on settings: a sealing station run with too much jaw temperature eats PTFE tape and heaters, and a cartoner fed with out-of-spec cartons wears its suction cups early - which is why our cartoner troubleshooting guide is also a guide to lower spares spend.
On a complete line the list is consolidated: one drive type, one valve series and one sensor family across machines means one spare covers several machines, and the store holds fewer, faster-moving items.
What we keep in Pune - and how fast it moves
For machines we build ourselves, we stock the fast-moving parts in Pune: the wear parts and common electrical and pneumatic items that appear on most of our spares lists. Parts we machine in-house are different - there are too many sizes to stock all of them - so we keep the manufacturing drawings and 3D models of every machine we deliver. A worn star wheel or a damaged guide can be remade from the drawing, even years later, without reverse-engineering it from a broken sample.
Availability and price confirmed within one working day of your enquiry. Stocked parts dispatched from Pune within two working days of a confirmed order. Machined parts remade from our drawings, typically in one to three weeks depending on size and material.
Export spares kit
For export machines, a commissioning spares kit - the wear parts and consumables most likely to be needed in the first months - is packed with the machine and listed on the packing list. Couriering a vacuum cup across the world costs more in time than in money, so we would rather it is already in your store. The full recommended kit for one or two years of running can be quoted with the machine and shipped in the same container - see how an MEF project runs for how it is packed and listed.
How to order a spare part
The fastest orders are the ones we can identify without a phone call. Send:
- Machine serial number from the nameplate on the machine or panel.
- Part number from the BOM or spares list, or the drawing number for a machined part.
- A photo of the part in place and of any label on it - especially for sensors, valves and belts.
- Quantity, delivery address and billing details (GSTIN for Indian customers).
WhatsApp to +91 8767639436 or email to sales@mefautomation.com both work; a photo on WhatsApp is often the quickest way to confirm the right part. For a breakdown, say so in the first line - urgent orders are handled first.
Obsolescence: when a PLC or servo is discontinued
Electronic components have lifecycles. Manufacturers announce when a product enters phase-out, sell it as a spare for a period, then stop - as Siemens has done with the older S7-300 PLC family. A packaging machine is expected to run for 10-15 years or more, so at least one control component will usually be discontinued during its life. Handled early, this is a planned upgrade; handled late, it is an emergency.
- We track lifecycle notices for the PLCs, HMIs and drives we use and tell customers when a part on their machine is announced for phase-out.
- For each announcement we propose an option: buy a last-time spare, or migrate to the successor model with converted software.
- We keep a copy of the final PLC and HMI software for each machine, so a replacement controller can be loaded without starting from scratch.
- For validated machines, a migration is a change under your change control, with a short test plan and updated documents.
- Customers on an AMC get a lifecycle review of their installed components as part of the annual visit.
Setting up your own spares store: ABC and a min-stock rule
You do not need an ERP system to run a sensible spares store. Rank each part by the damage its absence does:
| Rank | Rule | Policy |
|---|---|---|
| A | Stops the line and cannot be bought locally within a day | Always keep at least one, regardless of usage |
| B | Stops the line but is available locally within one or two days | Keep a small stock of the fast movers |
| C | Does not stop the line, or is available off the shelf | Buy as needed |
For wear and consumable parts, set a minimum stock and reorder when you reach it:
Example: a cartoner uses 6 suction cups a week and the lead time is 2 weeks. Usage during the lead time is 6 × 2 = 12. Add one week's usage as safety stock (6) and the minimum becomes 18. When the bin drops to 18, order a batch - say another 24. For a slow-moving critical part such as a servo drive, usage is close to zero, so the ABC rank decides: keep one.
Keeping spares in the machine's original packaging with no label linking them to the BOM; storing rubber suction cups and belts in hot, sunny stores where they age; and taking a part from stock without reordering. A simple bin card or spreadsheet prevents all three.