On this page
The twelve phases at a glance
Every project we run follows the same sequence, whether it is one cartoner or a complete bottle line. Durations below are typical ranges; your project schedule, issued at kick-off, replaces them with dates.
| Phase | Typical duration | Main deliverable | Your part |
|---|---|---|---|
| 1. Enquiry and samples | 1-2 weeks | Feasibility note, sample trial report or video | Send product, containers, closures, cartons, target output |
| 2. URS review, proposal and layout | 1-3 weeks | Technical proposal, layout drawing, URS compliance matrix | Share URS; check layout against the site |
| 3. Order and kick-off | About 1 week | Kick-off minutes, project schedule, document list | PO, advance, a named project owner |
| 4. Design and DQ | 2-4 weeks | GA drawing, electrical and pneumatic schematics, functional specification, change-part drawings, DQ document | Approve drawings on time |
| 5. Manufacture and integration | 6-12 weeks | Machined parts, assembly, panel wiring, PLC/HMI software, internal dry runs | Deliver FAT materials; freeze artwork |
| 6. FAT in Pune | 2-5 days per machine; 1-2 weeks for a line | Signed FAT protocol and report, punch list | Attend in person or by video, with QA |
| 7. Packing and shipping | Road transit in India; add sea freight for export | Packing list, export documents, seaworthy packing | Unloading; customs clearance at destination |
| 8. Installation | 2-5 days per machine; 1-3 weeks for a line | Installation record | Utilities, floor, rigging ready |
| 9. SAT and commissioning | 2-5 days per machine; 1-2 weeks for a line | SAT report, IQ/OQ execution support | Materials and product for trials |
| 10. Training | 1-3 days | Training records and material | Release operators and technicians |
| 11. Handover | At SAT | Final dossier: as-built drawings, BOM, manuals, software backup, certificates | Store under document control |
| 12. Warranty and support | Typically 12 months | Warranty terms, spares list, AMC offer | Follow the PM schedule; report faults with photos |
What happens in the phases that matter most
Samples and URS
The cheapest place to find a problem is on your sample material. Bottles that topple on a conveyor, cartons with a tight tuck flap or film that will not seal at the target speed all show up in a trial. A clear user requirement specification then fixes output, formats, materials of construction, controls and documents in writing, and our proposal answers it line by line.
Design freeze
Design ends with drawings you approve. After that point - the design freeze - every change to formats, speeds or options goes through written change control with its impact on cost and dates stated. Changes are possible; unrecorded changes are what break schedules.
Manufacture and FAT
Long-lead items such as robots, vision cameras and servo sets are ordered at kick-off, not when drawings are complete. The machine is then built, wired, programmed and dry-run internally before you are invited. The factory acceptance test runs your materials against the agreed protocol, including alarms, interlocks, format changes and, for pharma, user levels and audit trail. The machine ships only when the punch list is closed or each open point has an agreed owner and date.
Installation, SAT and training
On site our engineers level and anchor the machine, connect utilities, re-check the functions that transport could affect, and run the site acceptance test. Training is split: operators learn running, format change and cleaning; maintenance staff learn the drive, PLC and pneumatic diagnostics, the spares list and the preventive maintenance schedule.
Shipping and export packing
Domestic machines usually travel by road on a closed truck, bolted to skids with loose parts boxed and labelled. Export machines are packed in seaworthy wooden crates with ISPM-15 treated timber, vapour-barrier wrapping and desiccant, because a month in a container through humid ports is hard on bright steel and electronics. Change parts, the spares kit and documents are packed separately and listed on the packing list, so nothing is lost at customs inspection.
Warranty and after handover
Warranty starts at the point written in the contract, usually commissioning. During warranty the machine should run on the preventive maintenance schedule we hand over, and faults should be reported with the machine serial number, alarm text and photos or a short video, which lets most issues be diagnosed before anyone travels. After warranty, support continues through spare parts and optional AMC and remote support.
Lead time: when the clock actually starts
Lead time is counted from the day the project has everything it needs, which is usually later than the PO date. Four inputs start the clock: a signed-off URS or technical specification, an approved layout, the advance payment and the sample materials.
| Scope | Typical time to FAT-ready | Then add |
|---|---|---|
| Single standard machine | 8-12 weeks | Transit, 1-2 weeks on site |
| Customised machine or new format family | 12-16 weeks | Transit, 1-2 weeks on site |
| Complete line | 12-20 weeks | Transit, 1-4 weeks on site |
For export, add packing time, sea freight and customs clearance at both ends. Plan the site installation window only after the vessel is booked, not from the FAT date.
What you prepare before FAT and installation
Most of the schedule risk sits with things only the customer can provide. We send this list at kick-off and review it at every progress meeting:
- Power: supply as per the electrical load list (in India usually 415 V, 3-phase, 50 Hz) with a proper earth, cabled to the panel position.
- Compressed air: clean, dry, oil-free air at the pressure and flow stated on the utility list, piped to each machine with an isolation valve.
- Water and drains for washers, and extraction where powders or glue fumes are involved.
- Floor: level, able to take the machine weight, marked to the approved layout, with door openings wide and high enough for the largest crate.
- FAT materials: enough containers, closures, cartons, leaflets, labels or film for setting plus the test runs.
- Trial materials on site for SAT and the first production runs, including product or placebo.
- People: named operators from each shift, an electrical and a mechanical technician, and QA for validated projects.
- IT approval if remote support will be used, so the router can be connected at commissioning.
A useful estimate is rated speed × test minutes, plus 25-30% for setting and format changes. For a 100 packs/min cartoner with a 30-minute run on each of two formats: 100 × 30 × 2 = 6,000, plus 30% gives about 7,800 cartons, with matching leaflets and bottles or blisters.
Common delay causes and how to avoid them
| Cause | Typical effect | How to avoid it |
|---|---|---|
| Late samples or packaging material | Change parts cannot be finalised; FAT slips | Send production-standard samples with the enquiry; order FAT material at kick-off |
| Carton or bottle dimensions change after freeze | Change parts remade; software re-tested | Freeze artwork and dieline before design approval; route changes through change control |
| Slow drawing approval | Manufacturing waits | Agree a review period (for example five working days) at kick-off |
| Site not ready | Engineers on site with nothing to connect | Utility checklist signed before dispatch; photos of the prepared area |
| Imported component lead times | Assembly waits for robots, cameras or drives | Order long-lead items at kick-off; use standard parts with local stock |
| Validation documents reviewed late | FAT or IQ/OQ execution postponed | QA reviews protocols during manufacture, not the week of FAT |
Validated projects: fitting FAT and SAT into qualification
For pharma customers, the project phases map directly onto the qualification lifecycle. The URS is the reference; design review becomes DQ; FAT and SAT produce evidence that can support IQ and OQ. EU GMP Annex 15 allows FAT tests not to be repeated at IQ/OQ where it can be shown that transport and installation do not affect the function - so a well-documented FAT genuinely saves time on site. How that evidence is structured is explained in our guides to IQ, OQ and PQ and MEF's validation support.
The same applies to lines: a turnkey line with one documentation set is one qualification package, not five.
Frequently asked questions
How long does it take to deliver a packaging machine in India?
What do we need to provide for a factory acceptance test?
Can we attend FAT remotely?
Who installs and commissions the machine at an export site?
What documents do we receive at handover?
References