From URS to Production: How an MEF Project Runs

Twelve phases, from the first sample to the end of warranty. What happens in each, how long it typically takes, what you receive - and what you need to have ready so the schedule holds.

By MEF Automation Engineering TeamUpdated 8 min read
In short
  • A typical project has twelve phases from enquiry to warranty; each ends with a named deliverable someone signs.
  • Complete lines typically take 12-20 weeks from technical sign-off and advance to FAT-ready; single machines are faster.
  • The clock really starts when samples, URS, layout approval and advance are all in place - not on the PO date.
  • Most delays come from late materials, changes after design freeze and a site that is not ready - all avoidable with a shared checklist.
On this page
  1. The twelve phases at a glance
  2. What happens in the phases that matter most
  3. Lead time: when the clock actually starts
  4. What you prepare before FAT and installation
  5. Common delay causes and how to avoid them
  6. Validated projects: fitting FAT and SAT into qualification
  7. Frequently asked questions
  8. References

The twelve phases at a glance

Every project we run follows the same sequence, whether it is one cartoner or a complete bottle line. Durations below are typical ranges; your project schedule, issued at kick-off, replaces them with dates.

PhaseTypical durationMain deliverableYour part
1. Enquiry and samples1-2 weeksFeasibility note, sample trial report or videoSend product, containers, closures, cartons, target output
2. URS review, proposal and layout1-3 weeksTechnical proposal, layout drawing, URS compliance matrixShare URS; check layout against the site
3. Order and kick-offAbout 1 weekKick-off minutes, project schedule, document listPO, advance, a named project owner
4. Design and DQ2-4 weeksGA drawing, electrical and pneumatic schematics, functional specification, change-part drawings, DQ documentApprove drawings on time
5. Manufacture and integration6-12 weeksMachined parts, assembly, panel wiring, PLC/HMI software, internal dry runsDeliver FAT materials; freeze artwork
6. FAT in Pune2-5 days per machine; 1-2 weeks for a lineSigned FAT protocol and report, punch listAttend in person or by video, with QA
7. Packing and shippingRoad transit in India; add sea freight for exportPacking list, export documents, seaworthy packingUnloading; customs clearance at destination
8. Installation2-5 days per machine; 1-3 weeks for a lineInstallation recordUtilities, floor, rigging ready
9. SAT and commissioning2-5 days per machine; 1-2 weeks for a lineSAT report, IQ/OQ execution supportMaterials and product for trials
10. Training1-3 daysTraining records and materialRelease operators and technicians
11. HandoverAt SATFinal dossier: as-built drawings, BOM, manuals, software backup, certificatesStore under document control
12. Warranty and supportTypically 12 monthsWarranty terms, spares list, AMC offerFollow the PM schedule; report faults with photos

What happens in the phases that matter most

Samples and URS

The cheapest place to find a problem is on your sample material. Bottles that topple on a conveyor, cartons with a tight tuck flap or film that will not seal at the target speed all show up in a trial. A clear user requirement specification then fixes output, formats, materials of construction, controls and documents in writing, and our proposal answers it line by line.

Design freeze

Design ends with drawings you approve. After that point - the design freeze - every change to formats, speeds or options goes through written change control with its impact on cost and dates stated. Changes are possible; unrecorded changes are what break schedules.

Manufacture and FAT

Long-lead items such as robots, vision cameras and servo sets are ordered at kick-off, not when drawings are complete. The machine is then built, wired, programmed and dry-run internally before you are invited. The factory acceptance test runs your materials against the agreed protocol, including alarms, interlocks, format changes and, for pharma, user levels and audit trail. The machine ships only when the punch list is closed or each open point has an agreed owner and date.

Installation, SAT and training

On site our engineers level and anchor the machine, connect utilities, re-check the functions that transport could affect, and run the site acceptance test. Training is split: operators learn running, format change and cleaning; maintenance staff learn the drive, PLC and pneumatic diagnostics, the spares list and the preventive maintenance schedule.

Shipping and export packing

Domestic machines usually travel by road on a closed truck, bolted to skids with loose parts boxed and labelled. Export machines are packed in seaworthy wooden crates with ISPM-15 treated timber, vapour-barrier wrapping and desiccant, because a month in a container through humid ports is hard on bright steel and electronics. Change parts, the spares kit and documents are packed separately and listed on the packing list, so nothing is lost at customs inspection.

Warranty and after handover

Warranty starts at the point written in the contract, usually commissioning. During warranty the machine should run on the preventive maintenance schedule we hand over, and faults should be reported with the machine serial number, alarm text and photos or a short video, which lets most issues be diagnosed before anyone travels. After warranty, support continues through spare parts and optional AMC and remote support.

Lead time: when the clock actually starts

Lead time is counted from the day the project has everything it needs, which is usually later than the PO date. Four inputs start the clock: a signed-off URS or technical specification, an approved layout, the advance payment and the sample materials.

ScopeTypical time to FAT-readyThen add
Single standard machine8-12 weeksTransit, 1-2 weeks on site
Customised machine or new format family12-16 weeksTransit, 1-2 weeks on site
Complete line12-20 weeksTransit, 1-4 weeks on site
Planning an export shipment

For export, add packing time, sea freight and customs clearance at both ends. Plan the site installation window only after the vessel is booked, not from the FAT date.

What you prepare before FAT and installation

Most of the schedule risk sits with things only the customer can provide. We send this list at kick-off and review it at every progress meeting:

  • Power: supply as per the electrical load list (in India usually 415 V, 3-phase, 50 Hz) with a proper earth, cabled to the panel position.
  • Compressed air: clean, dry, oil-free air at the pressure and flow stated on the utility list, piped to each machine with an isolation valve.
  • Water and drains for washers, and extraction where powders or glue fumes are involved.
  • Floor: level, able to take the machine weight, marked to the approved layout, with door openings wide and high enough for the largest crate.
  • FAT materials: enough containers, closures, cartons, leaflets, labels or film for setting plus the test runs.
  • Trial materials on site for SAT and the first production runs, including product or placebo.
  • People: named operators from each shift, an electrical and a mechanical technician, and QA for validated projects.
  • IT approval if remote support will be used, so the router can be connected at commissioning.
How much FAT material?

A useful estimate is rated speed × test minutes, plus 25-30% for setting and format changes. For a 100 packs/min cartoner with a 30-minute run on each of two formats: 100 × 30 × 2 = 6,000, plus 30% gives about 7,800 cartons, with matching leaflets and bottles or blisters.

Common delay causes and how to avoid them

CauseTypical effectHow to avoid it
Late samples or packaging materialChange parts cannot be finalised; FAT slipsSend production-standard samples with the enquiry; order FAT material at kick-off
Carton or bottle dimensions change after freezeChange parts remade; software re-testedFreeze artwork and dieline before design approval; route changes through change control
Slow drawing approvalManufacturing waitsAgree a review period (for example five working days) at kick-off
Site not readyEngineers on site with nothing to connectUtility checklist signed before dispatch; photos of the prepared area
Imported component lead timesAssembly waits for robots, cameras or drivesOrder long-lead items at kick-off; use standard parts with local stock
Validation documents reviewed lateFAT or IQ/OQ execution postponedQA reviews protocols during manufacture, not the week of FAT

Validated projects: fitting FAT and SAT into qualification

For pharma customers, the project phases map directly onto the qualification lifecycle. The URS is the reference; design review becomes DQ; FAT and SAT produce evidence that can support IQ and OQ. EU GMP Annex 15 allows FAT tests not to be repeated at IQ/OQ where it can be shown that transport and installation do not affect the function - so a well-documented FAT genuinely saves time on site. How that evidence is structured is explained in our guides to IQ, OQ and PQ and MEF's validation support.

The same applies to lines: a turnkey line with one documentation set is one qualification package, not five.

Frequently asked questions

How long does it take to deliver a packaging machine in India?
A standard single machine is typically 8-12 weeks from technical sign-off and advance to FAT-ready, a customised machine 12-16 weeks and a complete line 12-20 weeks. Road transit and one to four weeks of installation, SAT and training follow. The biggest variables are sample availability, drawing approval time and imported components such as robots.
What do we need to provide for a factory acceptance test?
Production-standard packaging materials - containers, closures, cartons, leaflets, labels or film - in enough quantity for setting and the test runs, plus product or placebo where needed. A useful estimate is rated speed times test minutes, plus 25-30% for setting. You also need the approved FAT protocol and people who can sign it, ideally including QA.
Can we attend FAT remotely?
Yes. A video FAT with a live camera, screen sharing of the HMI and signed protocols works well for standard machines and repeat orders. For a first machine, a new format or a validated line, we recommend at least one person on site in Pune, because handling the machine and materials yourself reveals things a camera does not.
Who installs and commissions the machine at an export site?
Our engineers travel to install, commission, run SAT and train, in India and abroad. The customer arranges unloading, positioning equipment, utilities and any site permits. Travel, visa and accommodation costs are set out in the quotation so there are no surprises when the machine arrives.
What documents do we receive at handover?
A final dossier with as-built GA and electrical drawings, pneumatic schematics, the BOM with manufacturer part numbers, operation and maintenance manuals, signed FAT and SAT reports, material and calibration certificates, a recommended spares list, a preventive maintenance schedule and a backup of the PLC and HMI software.

References

  1. EU GMP Annex 15: Qualification and Validation

Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.

Want a schedule for your project?

Send your URS or a short description of product, packs and output. We will reply with a phase plan, the utilities and materials list, and a realistic lead time.