IQ, OQ and PQ for Packaging Machines: A Practical Guide

What EU GMP Annex 15 actually asks for at each qualification stage, with example tests and acceptance criteria for a cartoner, a bottle filling line and a vision system - and the mistakes that send protocols back for rework.

By MEF Automation Engineering TeamUpdated 8 min read
In short
  • IQ proves the machine is installed as designed, OQ proves it works across its operating range, PQ proves it performs reproducibly with your product.
  • Annex 15 §7 expects primary packaging equipment to be qualified at the minimum and maximum of critical parameters such as temperature, machine speed and sealing pressure - not just at nominal.
  • The 'three consecutive batches' rule belongs to process validation (§5.20). Three PQ runs for equipment is a convention; justify your number by risk.
  • Well-run FAT results can reduce on-site testing, and a requalification plan plus change control keep the qualified state alive.
On this page
  1. The qualification lifecycle, from URS to PQ
  2. IQ, OQ and PQ defined
  3. What goes into each stage: cartoner, filling line, vision system
  4. Annex 15 section 7: what is specific to packaging equipment
  5. The 'three batches' myth
  6. Requalification, change control and PIC/S PI 006-4
  7. Common qualification mistakes
  8. Frequently asked questions
  9. References

The qualification lifecycle, from URS to PQ

EU GMP Annex 15 (in force since October 2015) sets out qualification as a chain in which each stage is tested against the one before it. The URS is the reference point for the whole chain.

  1. URS (§3.2) - what the machine must do, written by the user and referred to throughout the lifecycle.
  2. DQ (§3.3) - documented check that the supplier's design meets the URS, before build.
  3. FAT (§3.4-3.5) - testing at the supplier's works against the URS/functional specification before shipment.
  4. SAT (§3.7) - confirmation at your site after delivery; justified FAT tests need not be repeated (§3.6).
  5. IQ (§3.9) - installation verified against drawings and specifications.
  6. OQ (§3.11-3.12) - functions tested across the operating range, including limits and worst case.
  7. PQ (§3.13-3.14) - performance with production materials under normal operating conditions.

In practice FAT, SAT and IQ/OQ overlap. A well-written FAT can carry a large share of OQ testing, provided it had approved acceptance criteria and recorded evidence.

IQ, OQ and PQ defined

The Annex 15 glossary definitions, paraphrased, with the question each stage answers:

StageAnnex 15 meaningThe question it answersTypical evidence
DQDocumented verification that the proposed design is suitable for its intended purposeWill this design meet our URS?URS response, FS/DS, traceability matrix
IQDocumented verification that equipment, as installed or modified, complies with the approved design and the manufacturer's recommendationsIs what arrived what we ordered, installed correctly?As-built drawings, material and calibration certificates, software versions, utility checks
OQDocumented verification that equipment performs as intended throughout its anticipated operating rangesDoes every function work, at the limits too?Executed test scripts, alarm and interlock challenges, reject challenges
PQDocumented verification that equipment performs effectively and reproducibly with the approved process and product specificationDoes it make good packs, run after run, with our product?Production runs, sampling results, in-process checks

Annex 15 §3.12 adds a useful point: successful OQ should allow SOPs, operator training and preventive maintenance requirements to be finalised. If your SOPs are still drafts at PQ, the order is wrong.

What goes into each stage: cartoner, filling line, vision system

The acceptance criteria below are examples to show the level of precision expected. Set yours from your URS, product specification and risk assessment.

Pharma cartoner

StageExample testExample acceptance criterion
IQInstallation vs as-built GA and electrical drawings; PLC/HMI versions vs software recordNo unresolved discrepancy; versions and checksums match
OQMissing-leaflet challenge: 20 cartons without leaflet seeded at random at maximum speed20/20 rejected, each confirmed in the reject bin
OQGuard door opened during runningMachine stops; cannot restart until door closed and reset acknowledged
PQThree runs per critical format at rated speed with production cartons, leaflets and productZero defective cartons in accepted output; coding legible; challenge samples rejected at start and end

Bottle filling and capping line

StageExample testExample acceptance criterion
IQCompressed air pressure and quality at the machine; product-contact parts vs material certificatesAs specified in URS; SS316L confirmed by 3.1 certificate
OQFill volume per nozzle with water or placebo at minimum and maximum speedEvery nozzle within the set tolerance, for example ±1% of nominal
OQNo-bottle-no-fill and no-cap-no-capping interlocksNo dispense and no cap chuck operation without container
PQProduction runs with fill-weight and cap-torque sampling at start, middle and endAll samples within product specification

Vision inspection system

StageExample testExample acceptance criterion
IQCamera, lens and lighting models; software and firmware versions; user levels configuredMatch approved specification and role table
OQChallenge set of known-bad samples (wrong code, smudged print, missing cap) plus known-good samples100% of bad samples rejected; false rejects on good samples within the agreed limit
OQInspection-limit change on the vision HMIAudit trail records user, time, old and new value and reason
PQProduction runs at rated speed with challenge samples inserted at start and endAll challenges rejected; read rate at or above the agreed target

Software functions - access levels, audit trail, e-signatures, backup and restore - are tested in OQ like any other function. The test set is in our 21 CFR Part 11 guide, and the depth should follow a risk assessment as described in GAMP 5 and CSV.

Annex 15 section 7: what is specific to packaging equipment

Annex 15 §7.1 notes that variation in equipment parameters, especially in primary packaging, can affect pack integrity - blister strips, sachets and sterile components are named - and so both primary and secondary packaging equipment must be qualified. §7.2 then sets the key rule: primary packaging equipment is qualified at the minimum and maximum operating ranges of the critical process parameters, such as temperature, machine speed and sealing pressure.

EquipmentTypical critical parameters to test at min and max
Blister packerForming and sealing temperature, sealing pressure, dwell time, machine speed
Sachet / stick pack sealerJaw temperature, jaw pressure, speed
Induction sealerPower setting, conveyor speed
Filling and cappingFilling speed, cap torque setting
Cartoner (secondary)Machine speed, leaflet and component feed, coding and inspection at speed

Combine them into worst cases. For a heat seal, low temperature at high speed is the obvious worst case for seal strength; high temperature at low speed is the worst case for material damage. Test both, and set the HMI limits to the range you actually qualified - a recipe that allows settings outside the qualified range undoes the work.

The 'three batches' myth

Many protocols require "three consecutive successful PQ batches" as if it were a regulation. The three-consecutive-batch expectation in Annex 15 §5.20 relates to process validation under the traditional approach, not to equipment PQ. Three PQ runs for a packaging machine is a common and sensible convention, not a legal requirement.

Justify the number by risk. A simple secondary-packaging machine running one format may need fewer runs; a primary packaging machine with several formats should cover worst-case formats (usually smallest and largest) and, per §3.14, worst-case batch sizes across the intended range. Write the rationale into the protocol so an inspector can see the number was chosen, not copied.

Requalification, change control and PIC/S PI 006-4

Annex 15 §4.1-4.2 requires equipment to be evaluated at an appropriate, justified frequency to confirm it remains in a state of control. §11 requires changes to be controlled and assessed for impact on the qualified state. For a packaging machine, typical requalification triggers are:

  • PLC, HMI or vision software changes beyond a documented, pre-approved configuration.
  • A new format or change part - qualify the new format and confirm existing ones are unaffected.
  • Replacement of a critical component with a non-identical part.
  • Relocation of the machine or major overhaul.
  • Trends in deviations, complaints or reject rates found in periodic review.

Retest what the change affects, based on a written impact assessment, rather than repeating everything. Keeping the original OQ scripts in a reusable form makes this cheap.

New PIC/S recommendations from 1 October 2026

PIC/S published PI 006-4, Recommendations on Qualification and Validation, on 30 July 2026. It becomes effective on 1 October 2026 and replaces PI 006-3. If your validation master plan or SOPs cite PI 006-3, update the reference at the next revision and check the new text against your current practice. For Indian plants, the revised Schedule M now also calls explicitly for DQ, IQ, OQ and PQ of equipment.

Common qualification mistakes

What sends protocols back for rework

Most of these are cheap to avoid at protocol-writing stage and expensive to fix after execution.

  • Vague acceptance criteria - "machine works satisfactorily" cannot fail, so it proves nothing.
  • Testing only at nominal settings, ignoring the min/max rule of §7.2.
  • No seeded-defect challenge for rejects and inspection - a reject system is only proved by making it reject.
  • IQ against superseded drawings, creating deviations that are really documentation errors.
  • Software version not recorded at IQ, so there is no baseline for change control.
  • Instruments not calibrated before OQ, which invalidates every measurement taken with them.
  • Using OEE or throughput as a PQ criterion - output is a commercial acceptance point; PQ is about quality and reproducibility.
  • Repeating every FAT test on site when §3.6 would have allowed justified reuse.

At MEF we draft IQ and OQ protocols with the machine's actual alarm list, limits and challenge tests built in; see our validation support for the full document set.

Frequently asked questions

What is the difference between IQ, OQ and PQ?
IQ verifies the machine is installed as designed: drawings, materials, utilities, calibration and software versions. OQ verifies every function works across the operating range, including limits and alarms. PQ verifies the machine performs reproducibly with your actual product and packaging materials under normal production conditions.
Is PQ always three batches?
No. The three-consecutive-batch expectation in EU GMP Annex 15 section 5.20 applies to process validation, not equipment PQ. Three PQ runs is a common convention. Choose the number by risk, cover worst-case formats and batch sizes, and document the rationale in the protocol.
Can OQ be done at the supplier's factory?
Partly. Annex 15 section 3.6 allows tests performed at FAT to stand without repetition at IQ/OQ if transport and installation do not affect the function. Tests that depend on your utilities, line integration or site network must still be done on site. The FAT needs approved acceptance criteria and recorded evidence to be reusable.
Does adding a new format part need requalification?
Usually a partial one. Through change control, assess the impact, then qualify the new format with the relevant OQ and PQ tests and confirm existing formats are unaffected. A full requalification is rarely needed if the original test scripts are reusable and the impact assessment is sound.
Who approves IQ OQ PQ protocols?
The regulated manufacturer's quality unit approves every protocol before execution and every report after it. The supplier can draft protocols and execute tests, and engineering and validation staff usually review them, but QA approval is what makes the qualification valid.

References

  1. EU GMP Annex 15: Qualification and Validation (2015)
  2. PIC/S: Revision of Recommendations on Qualification and Validation (PI 006-4)
  3. WHO TRS 1019 Annex 3: Good manufacturing practices - validation (2019)
  4. EU GMP Annex 11: Computerised Systems
  5. India Revised Schedule M, G.S.R. 922(E), 28 Dec 2023 (CDSCO)

Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.