The qualification lifecycle, from URS to PQ
EU GMP Annex 15 (in force since October 2015) sets out qualification as a chain in which each stage is tested against the one before it. The URS is the reference point for the whole chain.
- URS (§3.2) - what the machine must do, written by the user and referred to throughout the lifecycle.
- DQ (§3.3) - documented check that the supplier's design meets the URS, before build.
- FAT (§3.4-3.5) - testing at the supplier's works against the URS/functional specification before shipment.
- SAT (§3.7) - confirmation at your site after delivery; justified FAT tests need not be repeated (§3.6).
- IQ (§3.9) - installation verified against drawings and specifications.
- OQ (§3.11-3.12) - functions tested across the operating range, including limits and worst case.
- PQ (§3.13-3.14) - performance with production materials under normal operating conditions.
In practice FAT, SAT and IQ/OQ overlap. A well-written FAT can carry a large share of OQ testing, provided it had approved acceptance criteria and recorded evidence.
IQ, OQ and PQ defined
The Annex 15 glossary definitions, paraphrased, with the question each stage answers:
| Stage | Annex 15 meaning | The question it answers | Typical evidence |
|---|---|---|---|
| DQ | Documented verification that the proposed design is suitable for its intended purpose | Will this design meet our URS? | URS response, FS/DS, traceability matrix |
| IQ | Documented verification that equipment, as installed or modified, complies with the approved design and the manufacturer's recommendations | Is what arrived what we ordered, installed correctly? | As-built drawings, material and calibration certificates, software versions, utility checks |
| OQ | Documented verification that equipment performs as intended throughout its anticipated operating ranges | Does every function work, at the limits too? | Executed test scripts, alarm and interlock challenges, reject challenges |
| PQ | Documented verification that equipment performs effectively and reproducibly with the approved process and product specification | Does it make good packs, run after run, with our product? | Production runs, sampling results, in-process checks |
Annex 15 §3.12 adds a useful point: successful OQ should allow SOPs, operator training and preventive maintenance requirements to be finalised. If your SOPs are still drafts at PQ, the order is wrong.
What goes into each stage: cartoner, filling line, vision system
The acceptance criteria below are examples to show the level of precision expected. Set yours from your URS, product specification and risk assessment.
Pharma cartoner
| Stage | Example test | Example acceptance criterion |
|---|---|---|
| IQ | Installation vs as-built GA and electrical drawings; PLC/HMI versions vs software record | No unresolved discrepancy; versions and checksums match |
| OQ | Missing-leaflet challenge: 20 cartons without leaflet seeded at random at maximum speed | 20/20 rejected, each confirmed in the reject bin |
| OQ | Guard door opened during running | Machine stops; cannot restart until door closed and reset acknowledged |
| PQ | Three runs per critical format at rated speed with production cartons, leaflets and product | Zero defective cartons in accepted output; coding legible; challenge samples rejected at start and end |
Bottle filling and capping line
| Stage | Example test | Example acceptance criterion |
|---|---|---|
| IQ | Compressed air pressure and quality at the machine; product-contact parts vs material certificates | As specified in URS; SS316L confirmed by 3.1 certificate |
| OQ | Fill volume per nozzle with water or placebo at minimum and maximum speed | Every nozzle within the set tolerance, for example ±1% of nominal |
| OQ | No-bottle-no-fill and no-cap-no-capping interlocks | No dispense and no cap chuck operation without container |
| PQ | Production runs with fill-weight and cap-torque sampling at start, middle and end | All samples within product specification |
Vision inspection system
| Stage | Example test | Example acceptance criterion |
|---|---|---|
| IQ | Camera, lens and lighting models; software and firmware versions; user levels configured | Match approved specification and role table |
| OQ | Challenge set of known-bad samples (wrong code, smudged print, missing cap) plus known-good samples | 100% of bad samples rejected; false rejects on good samples within the agreed limit |
| OQ | Inspection-limit change on the vision HMI | Audit trail records user, time, old and new value and reason |
| PQ | Production runs at rated speed with challenge samples inserted at start and end | All challenges rejected; read rate at or above the agreed target |
Software functions - access levels, audit trail, e-signatures, backup and restore - are tested in OQ like any other function. The test set is in our 21 CFR Part 11 guide, and the depth should follow a risk assessment as described in GAMP 5 and CSV.
Annex 15 section 7: what is specific to packaging equipment
Annex 15 §7.1 notes that variation in equipment parameters, especially in primary packaging, can affect pack integrity - blister strips, sachets and sterile components are named - and so both primary and secondary packaging equipment must be qualified. §7.2 then sets the key rule: primary packaging equipment is qualified at the minimum and maximum operating ranges of the critical process parameters, such as temperature, machine speed and sealing pressure.
| Equipment | Typical critical parameters to test at min and max |
|---|---|
| Blister packer | Forming and sealing temperature, sealing pressure, dwell time, machine speed |
| Sachet / stick pack sealer | Jaw temperature, jaw pressure, speed |
| Induction sealer | Power setting, conveyor speed |
| Filling and capping | Filling speed, cap torque setting |
| Cartoner (secondary) | Machine speed, leaflet and component feed, coding and inspection at speed |
Combine them into worst cases. For a heat seal, low temperature at high speed is the obvious worst case for seal strength; high temperature at low speed is the worst case for material damage. Test both, and set the HMI limits to the range you actually qualified - a recipe that allows settings outside the qualified range undoes the work.
The 'three batches' myth
Many protocols require "three consecutive successful PQ batches" as if it were a regulation. The three-consecutive-batch expectation in Annex 15 §5.20 relates to process validation under the traditional approach, not to equipment PQ. Three PQ runs for a packaging machine is a common and sensible convention, not a legal requirement.
Justify the number by risk. A simple secondary-packaging machine running one format may need fewer runs; a primary packaging machine with several formats should cover worst-case formats (usually smallest and largest) and, per §3.14, worst-case batch sizes across the intended range. Write the rationale into the protocol so an inspector can see the number was chosen, not copied.
Requalification, change control and PIC/S PI 006-4
Annex 15 §4.1-4.2 requires equipment to be evaluated at an appropriate, justified frequency to confirm it remains in a state of control. §11 requires changes to be controlled and assessed for impact on the qualified state. For a packaging machine, typical requalification triggers are:
- PLC, HMI or vision software changes beyond a documented, pre-approved configuration.
- A new format or change part - qualify the new format and confirm existing ones are unaffected.
- Replacement of a critical component with a non-identical part.
- Relocation of the machine or major overhaul.
- Trends in deviations, complaints or reject rates found in periodic review.
Retest what the change affects, based on a written impact assessment, rather than repeating everything. Keeping the original OQ scripts in a reusable form makes this cheap.
PIC/S published PI 006-4, Recommendations on Qualification and Validation, on 30 July 2026. It becomes effective on 1 October 2026 and replaces PI 006-3. If your validation master plan or SOPs cite PI 006-3, update the reference at the next revision and check the new text against your current practice. For Indian plants, the revised Schedule M now also calls explicitly for DQ, IQ, OQ and PQ of equipment.
Common qualification mistakes
Most of these are cheap to avoid at protocol-writing stage and expensive to fix after execution.
- Vague acceptance criteria - "machine works satisfactorily" cannot fail, so it proves nothing.
- Testing only at nominal settings, ignoring the min/max rule of §7.2.
- No seeded-defect challenge for rejects and inspection - a reject system is only proved by making it reject.
- IQ against superseded drawings, creating deviations that are really documentation errors.
- Software version not recorded at IQ, so there is no baseline for change control.
- Instruments not calibrated before OQ, which invalidates every measurement taken with them.
- Using OEE or throughput as a PQ criterion - output is a commercial acceptance point; PQ is about quality and reproducibility.
- Repeating every FAT test on site when §3.6 would have allowed justified reuse.
At MEF we draft IQ and OQ protocols with the machine's actual alarm list, limits and challenge tests built in; see our validation support for the full document set.
Frequently asked questions
What is the difference between IQ, OQ and PQ?
Is PQ always three batches?
Can OQ be done at the supplier's factory?
Does adding a new format part need requalification?
Who approves IQ OQ PQ protocols?
References
- EU GMP Annex 15: Qualification and Validation (2015)
- PIC/S: Revision of Recommendations on Qualification and Validation (PI 006-4)
- WHO TRS 1019 Annex 3: Good manufacturing practices - validation (2019)
- EU GMP Annex 11: Computerised Systems
- India Revised Schedule M, G.S.R. 922(E), 28 Dec 2023 (CDSCO)
Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.