On this page
FAT vs SAT at a glance
EU GMP Annex 15 describes both. §3.4-3.5 say equipment, especially novel or complex equipment, may be evaluated at the vendor and confirmed against the URS or functional specification before installation. §3.7 says FAT may be supplemented by a SAT after the equipment arrives at the manufacturing site.
| FAT (Factory Acceptance Test) | SAT (Site Acceptance Test) | |
|---|---|---|
| Where | Supplier's assembly facility | Your plant, after installation |
| Purpose | Machine meets URS and FS before it ships | Machine arrived undamaged, is installed correctly and works in your line |
| Utilities | Supplier's power and air | Your power, air, network |
| Integration | Standalone, upstream/downstream simulated | Real upstream and downstream machines, SCADA, serialization |
| Cost of a fix | Low - parts, people and workshop are on hand | High - travel, air-freighted parts, lost production time |
| Typical duration | 1-3 days for a single machine; longer for a line | 1-3 days after installation and commissioning |
| Output | Signed FAT report, punch list, shipping release | Signed SAT report, handover to IQ/OQ |
The durations are typical ranges, not rules. A multi-machine turnkey line run together at FAT can take a week or more.
FAT runs on the supplier's power and air, in a stable workshop, with materials handled carefully. It cannot prove behaviour on your utilities, at your room humidity (which changes how cartons and leaflets fold and feed), with your upstream feed variation or on your network. Those belong in SAT.
What to test at FAT
FAT should cover everything that does not depend on your site. Test against the approved protocol and record evidence for each step.
- Documents vs machine: GA and electrical drawings, component list, material certificates for product-contact parts, software version record.
- Build quality: welds and finish in the product zone, cable routing, guarding, labelling, access for cleaning and maintenance.
- Every format and changeover: run each format; time at least one changeover performed by your operator, not the supplier's best technician.
- Performance run: continuous running at target speed on each critical format with production material, for the duration stated in the URS.
- Reject challenges: seeded defects for every inspection and reject function, with rejection confirmed.
- Safety: every guard switch, e-stop and safety function tested individually.
- Alarms and interlocks: each alarm triggered and its message and response checked.
- Software: user levels, audit trail, recipe handling, e-signatures, reports, power-failure recovery, backup and restore - see Part 11 tests.
What to test at SAT
SAT should concentrate on what transport, installation and your site could change. Repeating the whole FAT wastes days you usually do not have.
- Installation check: transport damage, levelling, anchoring, correct reassembly of parts removed for shipping.
- Utilities at the machine: supply voltage, earthing, air pressure and quality as specified.
- Safety circuits re-verified: every e-stop and guard switch after rewiring of any split cabinet or cable.
- Critical reject functions: seeded-defect challenge repeated, because sensors and cameras can shift in transit.
- Line integration: start, stop, accumulation and fault signals with upstream and downstream machines.
- Interfaces: SCADA, MES, time server, printers and serialization line controller on your network.
- Site performance run: at target speed in the real line, usually longer than at FAT.
- Training: operators, maintenance and administrators, with signed records.
Write SAT acceptance criteria in the same protocol format as FAT and approve them before the engineer arrives on site. If a site condition blocks a test - upstream machine not yet installed, network not ready - record it as an open item with an owner and a date rather than signing SAT as complete. An SAT signed with open integration tests usually resurfaces later as an IQ/OQ deviation.
Who should attend
| Role | FAT | SAT | Why |
|---|---|---|---|
| Production lead / senior operator | Yes | Yes | They will run it; they spot handling and changeover problems first |
| Maintenance engineer | Yes | Yes | Access, adjustability, spares, familiarity with the control system |
| QA / validation | Yes, or by video | Yes | Witnessing makes FAT results usable at IQ/OQ |
| Project engineer | Yes | Yes | Owns the URS and the punch list |
| Automation / IT | For Part 11 and network tests | Yes | User administration, backups, interfaces |
| EHS | Optional | Yes | Guarding and safety sign-off before production use |
A FAT attended only by purchasing and a consultant tends to pass machines that operators later struggle with. Changeover time measured with your operator is worth more than any demonstration.
How to prepare for FAT
- Approve the FAT protocol in advance, with test steps, acceptance criteria and signature blocks. A protocol agreed on the day tends to be written around what the machine does.
- Ship real product and packaging material in every size: containers, closures, cartons, leaflets, labels. A 60-minute run at 120 cartons/min uses 7,200 cartons per format; add 20-30% for setting and trials.
- Arrange a placebo where real product cannot leave your site, matching size, weight and flow behaviour as closely as possible.
- Prepare challenge samples: wrong codes, missing leaflets, empty cartons, smudged prints - labelled and counted.
- Request documents before travel: FS, drawings, software version record and certificates, so the document check is not done in a hurry.
- Agree punch-list categories and the shipping release criteria before testing starts.
Material arriving late is the most common reason a FAT slips. Our project delivery process fixes the material dispatch date at kick-off for that reason.
Punch lists and shipping release
Every FAT produces a punch list. The question is what must be closed before the machine leaves. Classify each item when it is raised:
| Category | Definition | Close by |
|---|---|---|
| A - Critical | A must requirement, GMP function or safety function fails | Before shipping, with retest witnessed in person or by video |
| B - Major | Function works but needs correction; no GMP or safety impact | Before shipping, or at SAT under a signed plan |
| C - Minor | Cosmetic, labelling or documentation issue | At SAT or with the final documents |
Agree in advance who assigns the category - normally the customer's project engineer, with QA deciding any item that touches a GMP function. Arguing about categories at the end of a long FAT day is how critical items get downgraded.
Shipping release criteria
- All category A items closed and retested; B items closed or accepted with a written plan.
- FAT report signed by both parties.
- Software frozen and backed up - the version that ships is the version that was tested.
- Change parts, tools and commissioning spares checked against the packing list (see spare parts).
- Machine photographed before packing; packing suited to transport mode and destination climate.
Avoiding repeat testing, and remote FAT
Test once where you can
Annex 15 §3.6 allows documentation review and some tests performed at FAT to stand without repetition at IQ/OQ, where it can be shown that transport and installation do not affect the function. Software logic, user levels, audit trail, recipe handling and report content usually qualify. Sensors, cameras, safety circuits, utilities and integration do not. Mark each FAT test in the protocol as "carry forward" or "repeat at site", get QA to agree the split, and reference the FAT evidence from your IQ and OQ protocols.
Remote and video FAT
| Advantages | Limitations |
|---|---|
| No travel cost or visa delays; faster scheduling | You see only what the camera shows |
| QA, IT and management can join for the parts they need | Hard to judge weld finish, noise, vibration and ergonomics |
| Recording can form part of the evidence | Network quality and time zones interrupt long runs |
If you choose remote FAT, agree a shot list in the protocol, use a hand-held camera alongside fixed ones, run the tests live, and ask for close-up photographs of the product zone. Plan a longer SAT to compensate for what you could not see.
At MEF, FAT is held at our Chikhali assembly facility in Pimpri-Chinchwad, and we offer live video FAT for customers who cannot travel. See what our validation support includes.
Frequently asked questions
What is the difference between FAT and SAT?
How long does a FAT take for a packaging machine?
Can FAT be done remotely by video?
Do FAT tests have to be repeated at SAT and IQ/OQ?
What materials should we send for a FAT?
References
- EU GMP Annex 15: Qualification and Validation (2015)
- WHO TRS 1019 Annex 3: Good manufacturing practices - validation (2019)
- ISPE GAMP 5 Guide, 2nd Edition (2022)
Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.