Who owns validation - and what a supplier should deliver
EU GMP Annex 15, WHO guidance and India's revised Schedule M all place qualification of equipment on the company that holds the manufacturing licence. You write or approve the URS, you approve every protocol, you sign every report, and you decide when a machine is fit for GMP use. No supplier can "validate" your machine for you. When a quotation says "validated machine", read it as "machine with validation documents".
What a supplier can and should do comes down to three things:
- Design a machine that meets your requirements and can be shown to meet them - testable functions, accessible instruments, a controlled software structure.
- Produce the evidence only the builder has: drawings, material certificates, calibration certificates, software records and test data.
- Help your team execute the tests efficiently, with protocols drafted in your format and an engineer who knows the machine.
EU GMP Annex 11 §3 expects formal agreements with suppliers of computerised systems and a risk-based decision on auditing them. GAMP 5 Second Edition (ISPE, 2022) encourages regulated companies to use supplier documentation and testing rather than repeat it. Both assume the supplier's documents are good enough to rely on. That is the standard we write to.
The exact scope for your project is fixed in the quotation and our URS response. Use the lists below as a checklist when you compare suppliers: if a document is not named in the offer, assume it is not included.
Before build: URS response, FS/DS, DQ and risk input
Most qualification problems are created before the first plate is cut. The documents in this phase make sure both sides agree on what is being built and how it will be proved.
| Document | What it contains | Who approves |
|---|---|---|
| URS compliance response | Every URS clause answered: Complies / Complies with deviation / Does not comply / Not applicable, with a reference to where the design meets it. Deviations are raised before order, not discovered at FAT. | Customer |
| Functional Specification (FS) | What the machine does: sequences, format range, speeds, alarms, interlocks, recipes, user levels, reports. | Customer |
| Design Specifications (DS) | Hardware: electrical schematics, pneumatic diagram, I/O list, network layout, component list with make and model. Software: PLC program structure, HMI screen list, recipe and data handling. | MEF; customer reviews |
| DQ support package | Traceability from URS to FS/DS, GA drawing, product-contact part list with material grades and finish, key component datasheets. | Customer executes and signs DQ |
| Risk-assessment input | Machine failure modes and their effects (missing leaflet, reject failure, camera trigger loss), which functions are GMP-critical, and the design controls for each. | Customer owns the risk assessment |
| Part 11 / Annex 11 compliance matrix | Each clause, how the machine meets it, and which parts are your procedural responsibility. | Customer |
| Traceability matrix | Each URS requirement linked to its FS/DS section and to the FAT, IQ or OQ test that proves it. | Customer |
Annex 15 §3.3 describes Design Qualification as documented verification that the design meets the URS, and Annex 11 §4.4 expects user requirements to be traceable through the lifecycle. The traceability matrix is how both are demonstrated in one document. We build it from the URS at kick-off and update it as tests are executed, so at the end of OQ every requirement shows a test and a result.
For the data-integrity side - logins, audit trail, e-signatures, backups - the compliance matrix follows the structure in our 21 CFR Part 11 guide.
FAT in Pune, SAT at your site
We draft the FAT protocol and send it for your approval before FAT, so the tests and acceptance criteria are agreed while changes are still cheap. FAT is run at our Chikhali assembly facility with your product and packaging material, witnessed by your team in person or by video. The output is a signed FAT report with raw evidence (counts, screenshots, printouts, reject samples) and a punch list, each item classified and closed before shipping or carried to site by agreement.
After installation, SAT confirms that the machine survived transport, that utilities are correct and that it works with your upstream and downstream equipment. See FAT vs SAT for what belongs at each stage.
Annex 15 §3.6 allows documentation review and some tests performed at FAT to stand without repetition at IQ/OQ, if it can be shown that transport and installation do not affect the function. That only works when the FAT had pre-approved acceptance criteria, recorded evidence and signatures. A FAT run as an informal demonstration has to be repeated in full on site.
IQ, OQ and PQ: we draft and help execute, your QA approves
Your validation team owns qualification. What we provide is the technical content and the hands to run the tests, so your team reviews and witnesses rather than writing scripts from scratch. The approach follows EU GMP Annex 15; see our IQ OQ PQ guide for the stage-by-stage detail.
| Stage | MEF provides | Your team does |
|---|---|---|
| IQ | Draft protocol in your format; verification checklists against as-built drawings; component and instrument list; calibration and material certificates; software and firmware version record; manuals. Engineer on site to support verification. | Approves the protocol, verifies, records deviations, signs the report. |
| OQ | Draft protocol with test scripts: alarms and interlocks, guard switches, e-stop, speed range, recipe load and save, access levels, audit trail, e-signature, power-failure recovery, backup and restore, reject challenge with seeded defects. Engineer executes the tests with QA witnessing. | Approves scripts and acceptance criteria, witnesses, reviews evidence, signs. |
| PQ | Technical input on worst-case settings, including the minimum and maximum of critical parameters that Annex 15 §7 expects for primary packaging equipment; attendance during runs; troubleshooting. | Writes and owns the PQ protocol, supplies product and materials, runs production, signs. |
We write drafts in your template where you have one. Where you do not, our standard format has numbered test steps, expected results, actual results, pass/fail, evidence reference and signature blocks - the structure most QA departments expect.
The handover dossier: what arrives with the machine
Annex 15 §3.9 lists what IQ should verify: installation against current drawings, collection of supplier manuals and maintenance requirements, calibration of instruments and verification of materials of construction. The handover dossier is built so that each of those checks has a document behind it.
| Item | Content | Used for |
|---|---|---|
| As-built drawings | GA, electrical schematics, pneumatic diagram and I/O list at final revision, reflecting every change made during FAT and SAT | IQ, maintenance, future change control |
| Material certificates | EN 10204 type 3.1 inspection certificates for SS316L product-contact parts, traceable to heat number; supplier declarations for gaskets and plastics in product contact | IQ materials-of-construction check |
| Calibration certificates | For machine-mounted measuring instruments (for example pressure gauges, temperature sensors, load cells), traceable to national standards | IQ, your calibration programme |
| Software version record | PLC and HMI program versions, firmware versions, backup file identities, software licence list; program backups on handover media | IQ, change control baseline, disaster recovery |
| Manuals | Operation, maintenance and troubleshooting manuals, recommended spares list | SOP writing, PM plans, spares planning |
| Training records | Attendees, content, trainer and date for operator, maintenance and administrator training, signed | Evidence that users are trained before GMP use |
| Executed FAT and SAT records | Signed reports, evidence and closed punch list | Referenced from IQ/OQ to avoid repeat testing |
Drawings issued at order stage are almost always out of date by SAT. An IQ that verifies a machine against superseded drawings creates a deviation on day one. Insist that the dossier carries final revisions.
Responsibility table: customer vs MEF
Unclear responsibility is the most common cause of qualification delay. We agree this split at kick-off and write it into the project plan (see our project delivery process).
| Activity | Customer | MEF |
|---|---|---|
| Validation master plan, validation policy | Owns | - |
| URS | Writes and approves | Reviews, clause-by-clause response |
| Risk assessment | Owns and approves | Technical input on failure modes |
| FS / DS | Reviews and approves FS | Writes |
| DQ | Executes and signs | Supplies design evidence and traceability |
| FAT | Approves protocol, witnesses, signs | Drafts protocol, executes, reports |
| SAT | Approves, witnesses, signs | Executes with your team |
| IQ / OQ | Approves protocols, witnesses, signs reports | Drafts protocols, supports execution |
| PQ | Writes, executes, signs | Technical support |
| User administration, SOPs, Part 11 procedures | Owns | Supplies role table and admin training |
| Change control, periodic review | Owns | Impact assessment, updated documents, test support |
After handover: change control and requalification
A machine stays validated only while it stays in a controlled state. Annex 15 §11 requires changes to be controlled, and Annex 11 §10 applies the same to computerised system configuration. Any change to PLC or HMI software, a new format part, or a replacement component that is not like-for-like goes through your change control. For those changes we provide:
- A technical impact assessment: what the change touches and which qualified functions could be affected.
- Updated FS, drawings and software version record, with a new version number and a change description.
- Test scripts for the affected functions, so you retest what changed rather than repeating the full OQ.
- For obsolete components, a written equivalence comparison of the old and new part.
Annex 15 §4 expects equipment to be re-evaluated at a justified frequency, and Annex 11 §11 asks for periodic evaluation of computerised systems. We support requalification with re-execution of OQ test scripts, instrument recalibration and a review of the software baseline against the last approved version. For ongoing support see AMC and remote support.
Frequently asked questions
Can a machine supplier validate our equipment for us?
What documents should a packaging machine supplier provide for IQ?
Do FAT results count towards IQ and OQ?
What is an EN 10204 3.1 certificate and why does it matter?
Who writes the IQ and OQ protocols, the supplier or the customer?
References
- EU GMP Annex 15: Qualification and Validation (2015)
- EU GMP Annex 11: Computerised Systems
- ISPE GAMP 5 Guide, 2nd Edition (2022)
- WHO TRS 1019 Annex 3: Good manufacturing practices - validation (2019)
- 21 CFR 211.68 - Automatic, mechanical, and electronic equipment
Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.