How to Write a URS for a Packaging Machine (with a Template Outline)

A good URS gets you comparable quotations, a smooth FAT and a short qualification. A vague one gets you change orders. Here is a section-by-section outline and the wording that makes each requirement testable.

By MEF Automation Engineering TeamUpdated 8 min read
In short
  • The URS is the reference point for the whole qualification lifecycle (EU GMP Annex 15 §3.2) and must be traceable through it (Annex 11 §4.4). Every later test traces back to it.
  • Write every requirement so it can pass or fail: a number, a condition and a method. 'High speed' and 'GMP design' cannot be tested.
  • A product and pack matrix with physical samples prevents the most expensive surprise: a format that does not run.
  • Put FAT acceptance criteria, documentation deliverables and Part 11 functions in the URS - not in a later email.
On this page
  1. What a URS is for
  2. A section-by-section URS template outline
  3. Vague vs testable: how to phrase requirements
  4. The product and pack matrix
  5. Utilities, GMP, data integrity and safety
  6. Put FAT acceptance criteria in the URS
  7. Common gaps that cause change orders
  8. Frequently asked questions
  9. References

What a URS is for

A User Requirement Specification states what the machine must do for you, in your terms, before any supplier proposes how. EU GMP Annex 15 §3.2 says the specification for equipment should be defined in a URS and/or functional specification, that essential quality elements and GMP risk mitigation should be built in at this stage, and that the URS is a point of reference throughout the validation lifecycle. For the control system, Annex 11 §4.4 asks for requirements that are risk-based and traceable through the lifecycle.

In practice the URS does four jobs:

  • Commercial - every supplier quotes against the same requirements, so quotations are comparable.
  • Design - the supplier's functional and design specifications answer it clause by clause, and DQ checks that answer.
  • Test - FAT, SAT, IQ and OQ acceptance criteria trace back to it (see IQ OQ PQ).
  • Contractual - when there is a dispute about scope, the approved URS and the supplier's response settle it.

Write it as a team: production (how it will be run), engineering and maintenance (utilities, layout, spares), QA (GMP and data integrity) and EHS (safety). QA approves it. A URS written by one person usually misses one of those four views.

A section-by-section URS template outline

This outline works for most pharma packaging machines - cartoners, bottle lines, blister and sachet machines, case packers and inspection systems. Delete sections that do not apply rather than leaving them empty, and state that you have done so.

SectionWhat to specify
1. ScopeMachine, its position in the line, what is included and explicitly excluded (feeding, conveyors, coding, serialization, software)
2. Product and pack matrixEvery product, container and pack format, with dimensions, tolerances, materials and samples
3. PerformanceSpeed per format, how speed is measured, changeover time, run duration for acceptance
4. Process requirementsSequence, critical parameters and their required ranges, in-process checks
5. Line integrationUpstream and downstream machines, signals exchanged, direction of flow, working height, layout limits
6. UtilitiesPower, compressed air, vacuum, water, network - values and tolerances
7. GMP and materialsMaterials of construction, surface finish, cleanability, lubricants, room classification
8. Control system and data integrityPLC/HMI make, user levels, audit trail, e-signatures, reports, backup, time synchronisation
9. Inspection and rejectEvery defect to detect, reject method, reject confirmation, challenge tests
10. Safety and complianceGuarding, e-stops, safety functions, electrical standards, CE marking for EU-bound machines
11. EnvironmentRoom temperature and humidity range, noise limit, floor loading, door and access dimensions
12. DocumentationSpecifications, drawings, certificates, manuals, protocols, formats and languages
13. Testing and acceptanceFAT and SAT scope, materials, duration and pass criteria
14. SupportTraining, spares, warranty, service response, software support after handover

Vague vs testable: how to phrase requirements

The test for every line: could two engineers watch the machine and agree whether it passed? If not, rewrite it. Include a number, the condition under which it applies, and ideally how it will be verified.

Vague (cannot fail)Testable (example wording)
High-speed machineMinimum 100 cartons/min sustained for 60 minutes on formats A and C, using approved production materials
GMP designProduct-contact parts SS316L with EN 10204 3.1 certificates; non-contact frame SS304; no painted surfaces in the product zone
Easy changeoverChangeover between any two formats by one trained operator in 30 minutes or less, with colour-coded change parts and no loose fasteners
21 CFR Part 11 compliantIndividual logins with four configurable levels; audit trail of recipe and parameter changes with old value, new value and reason; e-signature on batch report; PDF export
Rejects faulty cartonsRejects cartons with missing leaflet, missing product or unreadable code; reject confirmed by sensor; machine stops if a reject is not confirmed
Low noiseSound pressure level at operator position not above the plant limit (state the dB(A) value) at maximum speed

Must, should, nice-to-have

Classify every requirement. Must requirements are pass/fail: a supplier who cannot meet one is out, and each one is tested at FAT or qualification. Should requirements are scored when comparing offers. Nice-to-have items are included only if cost-neutral. Keep the must list tight and make every GMP-critical requirement a must. A URS in which everything is a must gives suppliers no signal about what really matters to you.

The product and pack matrix

Most change orders on packaging projects start with a format that was not specified, or a material that behaves differently from the drawing. List every combination the machine must run:

FormatContainerCarton (L × W × H, mm)LeafletTarget speed
A30 ml round PET bottle, Ø34 mm40 × 40 × 105Folded, 1 per carton120/min
B60 ml round PET bottle, Ø42 mm48 × 48 × 120Folded, 1 per carton100/min
C100 ml amber glass, Ø48 mm, with measuring cup55 × 55 × 140Folded, 1 per carton80/min

The figures above are illustrative. For each format also give dimensional tolerances, carton board grade and grammage, leaflet paper weight and fold pattern, and whether the carton is pre-glued. Then send physical samples - enough for the supplier's trials and the FAT - in every size. Drawings describe the nominal carton; samples show how your printer's cartons actually behave. If you are still choosing a machine type, our horizontal vs vertical cartoner guide shows how the matrix drives that choice.

Utilities, GMP, data integrity and safety

Utilities

State voltage, phases, frequency and tolerance, and the available compressed air pressure and quality. For export machines, specify the destination supply rather than assuming the supplier's home standard. Include network requirements if the machine connects to SCADA, MES or a serialization system.

GMP and materials

Specify product-contact and non-contact material grades, the certificates you need, surface finish where it matters, cleanability (no hidden threads or dead spaces in the product zone) and lubricant type where incidental contact is possible. See SS304 vs SS316 for where each grade makes sense.

Control system and data integrity

Name your preferred PLC and HMI platform if you standardise on one - maintenance teams trained on one brand should not inherit another by accident. List user levels, audit-trail content, e-signature points, report content and format, backup method and time synchronisation. Our Part 11 guide lists the functions worth specifying.

Safety

Require interlocked guarding, emergency stops at defined positions and any specific safety functions such as Safe Torque Off on servo drives. For machines going to the EU, specify CE marking. Machines placed on the EU market from 20 January 2027 fall under the new Machinery Regulation (EU) 2023/1230 instead of the Machinery Directive - see our CE marking guide.

Documentation deliverables

List every document, the format (your template or the supplier's), language and when it is due: FS/DS, compliance matrices, drawings, certificates, FAT/SAT/IQ/OQ protocols, manuals and training records. Our validation support page is a usable checklist.

Put FAT acceptance criteria in the URS

If FAT criteria are agreed only after the machine is built, they will be written around what the machine does. Define them up front:

  • Materials: your production cartons, leaflets and containers in all formats, supplied by a stated date.
  • Run length: for example 60 minutes continuous on each critical format at target speed.
  • What counts as a failure: any stop caused by the machine, as opposed to material defects or operator error, defined in advance.
  • Challenge tests: seeded defects for every reject function, with 100% rejection required.
  • Software tests: user levels, audit trail, recipe handling, power-failure recovery.
  • Documents that must be available at FAT: approved FS, drawings, software version record.

See FAT vs SAT for what to test at each stage.

Common gaps that cause change orders

Missing from most URS documents we receive

Each of these has turned into a cost or schedule change on real projects. Check for them before you issue the URS.

  • A format added after order - new change parts, new trials, sometimes a longer machine.
  • No line-integration signals - who stops whom when the downstream machine is full.
  • Room and access limits - ceiling height, door width, floor loading, service clearance.
  • "Serialization-ready" undefined - space, mounting, encoder, reject and line-controller interface; see serialization and aggregation.
  • Report and audit-trail format agreed only at FAT.
  • HMI language for export sites, and the language of manuals.
  • Protocol template - suppliers write in their own format unless you supply yours.

When we receive a URS, we return a clause-by-clause compliance response and raise every assumption and deviation as a question before quoting, so the gaps are closed on paper rather than on the shop floor.

Frequently asked questions

Who should write the URS for a packaging machine?
The user company, not the supplier. Production, engineering, maintenance, QA and EHS should all contribute, and QA approves it. Suppliers can review it and point out gaps or impossible requirements, but a URS written by the supplier tends to describe the supplier's standard machine rather than your needs.
What is the difference between a URS and a functional specification?
The URS says what you need, in your terms, independent of any supplier. The functional specification is the supplier's answer: how their machine will meet each requirement, including sequences, alarms and screens. DQ checks the functional and design specifications against the URS, and the traceability matrix links the two.
How detailed should a URS be?
Detailed enough that every requirement can pass or fail and every supplier quotes the same scope. For a pharma packaging machine that means a full product and pack matrix, numeric performance targets, utilities, materials, data-integrity functions, safety, documents and FAT criteria. It should not dictate design details you do not actually care about.
Can we use a supplier's URS template?
You can use one as a starting checklist, but rewrite it in your own terms and add your products, materials, site conditions and quality requirements. A template copied without editing often contains requirements that suit the supplier's standard machine and misses the ones that matter at your site.
Can the URS change after the purchase order?
Yes, through a controlled revision agreed by both sides, with the cost and schedule impact assessed. Changes after design freeze are expensive, and changes after FAT may require retesting. Freeze the product and pack matrix and the must requirements before ordering.

References

  1. EU GMP Annex 15: Qualification and Validation (2015)
  2. EU GMP Annex 11: Computerised Systems
  3. ISPE GAMP 5 Guide, 2nd Edition (2022)
  4. Regulation (EU) 2023/1230 on machinery
  5. 21 CFR Part 11 - Electronic Records; Electronic Signatures (eCFR)

Regulatory text changes. Always check the current version of a regulation before relying on it; this article reflects our reading as of 29 Sep 2026 and is not legal advice.